Contractor’s differing site condition claim denied because soils reports indicated difficult soils

(For a downloadable PDF of this “In Court,” click here.)

The uncertainty that contractors face regarding unknown subsurface conditions is the contractor’s greatest risk. This type of risk is inherent on most road and heavy construction projects, and is based on the fact that testing of subsurface conditions is expensive and limited. This results in conclusions being drawn from limited data. In addition, this risk is further highlighted by the fact that geotechnical engineering is uncertain and often described as part science and part art.

In light of this risk, most major standard form construction contracts contain a differing site conditions clause. These clauses typically allocate the risk of unknown site conditions to the owner that the contractor could not have reasonably anticipated based on the contract documents and/or site investigation. Differing site conditions clauses typically offer two separate bases for relief: Type I” clauses are based on site conditions that differ materially from the conditions indicated in the contract documents, while “Type II” clauses are based on site conditions that differ materially from those ordinarily encountered and recognized as inherent in the work.

In the recent case, Appeal of NDG Constructors (August 21, 2012), the Armed Services Board of Contract Appeals (ASBCA or Board) denied the claim of NDG for a Type I differing site condition. NDG contracted with the Army Corps of Engineers for $959,300 to tunnel a waterline underneath I-90 near Rapid City, South Dakota to serve Ellsworth Air Force Base. NDG’s work included constructing a 16 inch waterline under I-90 by tunneling and jacking approximately 560 linear feet of 54 inch steel casing. NDG subcontracted the tunneling portion to BT Construction, Inc. (BTC), a pipeline excavation contractor, for $706,000.

The contract documents incorporated two geotechnical reports from American Engineering Testing, Inc., including a total of seven borings, soil samples obtained in accord with ASTM procedures, and lab tests of the soil samples. During the work, NDG and BTC encountered difficult soil conditions that slowed their planned rate of progress, including due to shale rock, fat clays, and wet soils. NDG submitted a claim of $146,278.94 and 9 calendar days based on alleged Type I differing site conditions. The contracting officer denied NDG’s claim, and NDG appealed to the ASBCA.

In reviewing this matter, the ASBCA noted that Federal Acquisition Regulation 52.236-2(a)(1) provides that Type I differing site conditions consist of “subsurface or latent physical conditions at the site which differ materially from those indicated in th[e] contract.” In order to prove entitlement to a Type I differing site condition, NDG had to establish that:

[T]he conditions indicated in the contract differ materially from those actually encountered during performance; the conditions actually encountered were reasonably unforeseeable based on all information available to the contractor at the time of bidding; the contractor reasonably relied upon its interpretation of the contract and contract-related documents; and the contractor was damaged as a result of the material variation between expected and encountered conditions.