Tunnel Machine Hazel Completes 16-Month, 2.2-Mile Dig in Va.

Me Photo Headshot

Tunnel boring machine Hazel has completed her 2.2-mile journey 100 feet beneath the Potomac River and Old Town Alexandria, Virginia.

Her 16-month expedition culminated at 10 a.m. March 13 with the creation of a 12-foot-wide tunnel to prevent sewage from entering the Potomac and nearby creeks. The tunnel will be integrated into an upgraded wastewater treat plant that connects the city’s four combined sewer outfalls that date back to the 1860s.

tunnel machine hazel breaks through shaft to complete tunnelHazel emerges into a flooded shaft by the Potomac River to complete the 2.2-mile Waterfront Tunnel.AlexRenewThe tunnel is part of RiverRenew, the largest infrastructure project in Alexandria’s history.

The project’s goal is to upgrade the city’s overcapacity combined rainwater-sewage system. The system’s sewage-treatment capacity is often exceeded during rain, sending untreated sewage mixed with stormwater to four outfalls that discharge into river and local waterways.

Under state law, Alexandria must fix the pollution-discharge problem by July 1, 2025.

AlexRenew, the wastewater treatment authority for Alexandria and parts of Fairfax County, estimates the tunnel will capture over 120 millions gallons of sewage mixed with rainwater. The effluent will be treated at AlexRenew’s wastewater plant and then returned to the Potomac after it is cleaned, the authority says.

The new tunnel runs along Old Town’s riverfront and extends into the city parallel to the I-495 Woodrow Wilson Bridge. It ends at the AlexRenew wastewater plant.